“A story of incompetence, arrogance, privilege and power”: A brief history of the Garden Bridge

Ewwww. Image: Heatherwick.

Labour assembly member Tom Copley on an ignominious history.

The publication last week of the final bill for Boris Johnson’s failed Garden Bridge has once again pushed this fiasco into the headlines.

As well as an eye-watering £43m bill for taxpayers for this Johnsonian indulgence, what has been revealed this week is astonishing profligacy by the arms-length vehicle established to deliver it: the Garden Bridge Trust. The line by line account of their spending reveals £161,000 spent on their website and £400,000 on a gala fundraising event, amongst many other eyebrow raising numbers. 

Bear in mind that back in 2012, Johnson promised that the bridge would be entirely privately funded. The bridge’s most ardent advocate, Joanna Lumley, called it a “tiara for the Thames” and “a gift for London”. Today, the project would seem the very opposite of a “gift”.

The London Assembly has been scrutinising this project since its inception, and I now chair a working group tasked with continuing our investigation. We are indebted to the work of local campaigners around Waterloo as well as Will Hurst of the Architects Journal, who has brought many of the scandals surrounding the project into the open, and who was the subject of an extraordinary public attack by Johnson for doing so.

Yet every revelation about this cursed project has thrown up more questions than it has answers, and it’s worth reminding ourselves just how shady and rotten the story of this project has been.

There was Johnson’s £10,000 taxpayer funded trip to San Francisco to drum up sponsorship for the Thomas Heatherwick garden bridge design, despite the fact that TfL had not at that point even tendered for a designer for the project.

The design contest itself was a sham, with one of the two other architects TfL begged to enter in an attempt to create the illusion of due process later saying they felt “used”. Heatherwick Studios was awarded the contract and made a total of £2.7m from taxpayers from the failed project.


Soon after the bridge’s engineering contract had been awarded to Arup, it was announced that TfL’s then managing director of planning, Richard de Cani, was departing TfL for a new job – at Arup. He continued to make key decisions relating to the project while working his notice period, a flagrant conflict of interest that wouldn’t have been allowed in the civil service. Arup received more than £13m of taxpayer cash from the failed project.

The tendering process attracted such concern that the then Transport Commissioner, Peter Hendy, ordered an internal audit of it. The resulting report was a whitewash, and a far more critical earlier draft was leaked to the London Assembly.

As concerns about the project grew, so did the interventions by the bridge’s powerful advocates to keep it on track. Boris Johnson signed a mayoral direction which watered down the conditions the Garden Bridge Trust had to meet in order to gain access to further public money, exposing taxpayers to further risk. When he was hauled in front of the London Assembly to explain this decision, after blustering for while he finally told me that he couldn’t remember.

David Cameron overruled the advice of senior civil servants in order to extend the project’s government credit line. And George Osborne was at one point even more keen on the Garden Bridge than Johnson himself. The then chancellor was criticised by the National Audit Office for bypassing usual channels in order to commit funding to it. Strangely, none of the project’s travails have made it onto the pages of the London Evening Standard, a paper he now edits. Nor did they under his predecessor Sarah Sands, now editor of the Today Programme, another firm advocate for the Garden Bridge.

By 2016 the project appeared to be in real trouble. Yet the Garden Bridge Trust ploughed ahead in the face of mounting risks. In February 2016, despite having not secured the land on the south bank to actually build the bridge on, nor satisfied all their planning consents, the Trust signed an engineering contract. That decision alone has cost the taxpayer £21m.

Minutes of the Trust’s board meetings that I secured from TfL (after much wailing and gnashing of teeth from the Trust itself) reveal that weeks beforehand Thomas Heatherwick had urged the trustees to sign the contract in order to demonstrate “momentum”.

Meanwhile TfL, which was represented at board meetings by Richard de Cani and so should’ve been well aware of the mounting risks to the project, astonishingly failed to act in interests of taxpayers by shutting the project down.

Indeed, TfL allowed further public money to be released for the project despite the Trust not having satisfied at least two of the six conditions that had been set by TfL in order to protect the public purse. The decision to approve funding was personally approved by Transport Commissioner Mike Brown, who has never provided an adequate explanation for his decision.

The story of the Garden Bridge project is one of incompetence, arrogance and recklessness, but also of privilege and power. This was “the great and the good” trying to rig the system to force upon London a plaything for themselves wrapped up as a gift.

The London Assembly is determined to hold those responsible to account, and we will particularly focus on TfL’s role in this mess. However, this is not just a London issue, but a national scandal. There is a growing case for a Parliamentary inquiry into the project, and I would urge the Public Accounts Committee to launch an investigation. 

The Garden Bridge may seem like small beer compared to Brexit. But there is a common thread: Boris Johnson. It should appal and outrage us that this man is still being talked about as a potential future Prime Minister. His most expensive vanity project, now dead in the water, perhaps serves as an unwelcome prophecy for what may be to come should he ever enter Number 10.

Tom Copley is a Labour member of the London Assembly. 

 
 
 
 

Cycling on London’s Euston Road is still a terrifying experience

Cyclists on the Euston Road. Image: Jonn Elledge.

The New Road, which skirted the northern boundaries of London’s built up area, first opened in the 1750s. Originally, it was intended to link up outlying villages and provide a route to drive sheep and cows to the meat market at Smithfield without having to pass through the congested city centre. 

As with bypasses and ring roads the world over, however, it increasingly became congested in its own right. Today, you won’t often find livestock on the route, which is now Marylebone, Euston and City roads. But you will find up to six lanes of often stationary buses, cabs, and private vehicles. In a city whose centre is largely free of multi-lane highways, London’s northern ring road has long been the sort of abomination that you avoid at all costs.

But now, somewhat surprisingly, the road is seeing yet another new use. Earlier this week, the first phase of a temporary cycle lane opened on the Euston Road, the middle section of the route which runs for roughly a mile. As London rethinks roads throughout the city, this addition to the cycling map falls solidly into the category of streets that didn't seem like candidates for cycling before the pandemic.

It is, to be clear, temporary. That’s true of many of the Covid-led interventions that Transport for London is currently making, though those in the know will often quietly admit to hoping they end up being permanent. In this case, however, the agency genuinely seems to mean it: TfL emphasized in its press release that the road space is already being allocated for construction starting late next year and that "TfL will work with local boroughs to develop alternate routes along side streets" when the cycle lane is removed.

At lunchtime on Friday, I decided to try the lane for myself to understand what an unlikely, temporary cycle lane can accomplish. In this case it's clear that the presence of a lane only accomplishes so much. A few key things will still leave riders wanting:

It’s one way only. To be specific, eastbound. I found this out the hard way, after attempting to cycle the Euston Road westbound, under the naive impression that there was now a lane for me in which to do this. Neither I nor the traffic I unexpectedly found myself sharing space with enjoyed the experience. To be fair, London’s cycling commissioner Will Norman had shared this information on Twitter, but cyclists might find themselves inadvertently mixing with multiple lanes of much, much bigger vehicles.

It radically changes in width. At times the westbound route, which is separated from the motor traffic by upright posts, is perhaps a metre and a half wide. At others, such as immediately outside Euston station, it’s shared with buses and is suddenly four or five times that. This is slightly vexing.

It’s extremely short. The publicity for the new lane said it would connect up with other cycle routes on Hampstead Road and Judd Street (where Cycleway 6, the main north-south crosstown route, meets Euston Road). That’s a distance of roughly 925m. It actually runs from Gower Street to Ossulton Street, a distance of barely 670m. Not only does the reduced length mean it doesn’t quite connect to the rest of the network, it also means that the segregated space suddenly stops:

The junction between Euston Road and Ousslston Street, where the segregated lane suddenly, unexpectedly stops. Image: Jonn Elledge.

 

It’s for these reasons, perhaps, that the new lane is not yet seeing many users. Each time I cycled the length of it I saw only a handful of other cyclists (although that did include a man cycling with a child on a seat behind him – not something one would have expected on the Euston Road of the past).


Though I hesitate to mention this because it feeds into the car lobby’s agenda, it was also striking that the westbound traffic – the side of the road which had lost a lane to bikes – was significantly more congested than the eastbound. If the lane is extended, it could, counterintuitively, help, by removing the unexpected pinch points at which three lanes of cars suddenly have to squeeze into two.

There’s a distinctly unfinished air to the project – though, to be fair, it’s early days. The eastbound lane needs to be created from scratch; the westbound extended. At that point, it would hopefully be something TfL would be keen enough to talk about that cyclists start using it in greater numbers – and drivers get the message they should avoid the Euston Road.

The obvious explanation for why TfL is going to all this trouble is that TfL is in charge of the Euston Road, and so can do what it likes there. Building cycle lanes on side nearby roads means working with the boroughs, and that’s inevitably more difficult and time consuming.

But if the long-term plan is to push cyclists via side roads anyway, it’s questionable whether all this disruption is worth it. A segregated cycle lane that stops without warning and leaves you fighting for space with three lanes of buses, lorries, and cabs is a cycle lane that’s of no use at all.

Jonn Elledge was founding editor of CityMetric. He is on Twitter as @jonnelledge and on Facebook as JonnElledgeWrites.